Most solutions to this problem are essentially what the OP recognized as nakedly illegal---that is, exaggerating productive hours---but most contractors are savvy enough to do it in less auditable and more positively regarded ways, such as stretching out timelines (four 20-hour work weeks raise fewer flags than one 80-hour week), adding more chefs than the kitchen calls for, or funding unnecessary little side projects. Straight-up tampering with timecards is an impatient and dangerous way of achieving (IMO) the same wasteful evil as happens everywhere else in the public and private sector.
1 https://www.nrc.nl/nieuws/2024/02/15/het-subsidiepotje-moet-...
It’s also still a reasonable question to ask “well, last year we budgeted $15M and you got acceptable results while spending only $14M; perhaps you only need $14M/yr…” And despite its reasonableness, many people would prefer to oversee a $15M/yr budget.
It’s little surprise what happens under such a system: logical people over-reserve.