Doesn't stockpiling parts go against some of their core principles?
reply
Just In Time only works if you can correctly forecast the lead times for parts to arrive when requested.

e.g. if you know you use 20/day and it takes 2 days to get the new parts then you order parts when your inventory hits 40.

If the error bars on the delivery dates suddenly grow, you have to start ordering parts earlier.

So in a sense, yes, needing to hold inventory is against part of JIT but if your goal is to maximize resilience to inventory shortages or supply shocks then no, it's not against their core principles.

reply
> If the error bars on the delivery dates suddenly grow, you have to start ordering parts earlier

The entire point of JIT is to identify those widening error bars early and treat. In this case, by moving more work onshore.

reply
Sure.

The error bars inherently have a big of a lag due to it taking some time for the average time to catch up to the real world conditions.

Much like trading, you could use exponential and/or weighted moving averages to give you signal as things change.

reply
Not having the parts seems like a bigger violation.
reply
A friend of mine was employed at a company which was responsible for BMW seat production. If they had issues with their production lines, BMW was out of business within a few hours/days. I guess it makes sense to stock at least the most important parts.
reply
The principles really go down to reducing waste in the overall production process.

Stockpiling parts was one method routinely used to mask instances of waste, so they had deliberately worked to reduce inventory held in stock to force waste to become visible, so they could then address the causes of the waste.

But as long as the inventory doesn’t go stale on the shelf, it is a relatively minor waste compared to the other types, and certainly much better than the major waste of having no finished goods to sell into the market.

reply
Inventory on the shelf actually isn’t waste at all if it’s needed to stabilize the system from externalities.
reply
How do you differentiate waste caused by internalities (aka something you can potentially do something about) and externalities?

It requires some deep introspection, and is often error prone.

reply
Working through that depends upon the business and the maturity of their processes, and where they are on their lean journey. There's no universal answers in lean, just guiding principles.
reply
Pendulum swings.
reply
The fukushima plant workers performed incredibly during the disaster. They harvested batteries from the parking lot and used fire engine pumps. An excellent example of anti fragility.
reply
Anti fragile systems gain from stress and instability. Fukushima is not better off from getting hit by a tsunami.

This is a great example of initiative and resilience, but a pretty textbook example of a fragile system. A single major but predictable event overwhelmed all primary and backup systems leading to a global scale nuclear catastrophe.

reply
I agree that Fulushima was fragile, but it was not a ”global scale” catastrophe. It made the news everywhere, but aside from that the effects were quite local.
reply
The logistics impact on toyota was from the area closure and evac, not anything to do with the goings on at the actual nuclear plant. Any number of disasters could have had a similar impact.
reply
None of that has anything to do with the comment you replied to. Despite their valiant efforts, it was still a disaster.
reply
It’s also not what antifragile means.
reply
I work at a Toyota dealership and I can tell you with utmost certainty that they never have anything for anything new. Usually it's on backorder and you need to hunt for a factory or distro center that has it. Then it arrives broken in the box after FedEx or UPS throw it around like a ragdoll.
reply
That's really sad to hear :(
reply