upvote
(18GW * 1 day)/23 ~= 67TJ

Little Boy (the type of bomb dropped on Hiroshima) was 63TJ

reply
Where are you getting 18GW from? Last estimate I saw (for 2025) was 14.4 (125TWh continuous)

The IEA is projecting 500TWh (57GW ) by 2030 so it might be consistent with their figures.

reply
From the source of the 23 atomic bombs claim that was linked in beloch's comment - https://www.cbc.ca/news/canada/edmonton/wonder-valley-slcn-c...
reply
Ah, now I remember the original headline.

Now it has a bit at the bottom This story and its headline have been updated to provide further context about the preliminary nature of Robert Davies’ assessment and align with our journalistic standards and practices

I was thinking they were talking about current usage. Not guesses of how much something might use.

The only other source I found was https://majorprojects.alberta.ca/details/Wonder-Valley-AI-Da...

Indicating the initial build would be 1.4GW.

I'm not sure how much size matters of individual data centers apart from their contribution to the total. If they sum to the same amount, how much does it matter.

If it's true that you can build something of that size without an environmental impact report then there's something pretty wrong with the laws there.

reply
Probably 50 kilo grams of TNT, affectionately known as "Fart Man".
reply